TECHNICAL TRANSACTIONS 5/2017 CZASOPISMO TECHNICZNE 5/2017 CIVIL ENGINEERING

Podobne dokumenty
Krytyczne czynniki sukcesu w zarządzaniu projektami

Patients price acceptance SELECTED FINDINGS

EXAMPLES OF CABRI GEOMETRE II APPLICATION IN GEOMETRIC SCIENTIFIC RESEARCH

WYZNACZANIE WARTOŚCI WYPRACOWANEJ W INWESTYCJACH REALIZOWANYCH PRZEZ PODWYKONAWCÓW

WYDZIAŁ NAUK EKONOMICZNYCH. Studia II stopnia niestacjonarne Kierunek Międzynarodowe Stosunki Gospodarcze Specjalność INERNATIONAL LOGISTICS

Rozpoznawanie twarzy metodą PCA Michał Bereta 1. Testowanie statystycznej istotności różnic między jakością klasyfikatorów

TRANSPORT W RODZINNYCH GOSPODARSTWACH ROLNYCH

Proposal of thesis topic for mgr in. (MSE) programme in Telecommunications and Computer Science

CEE 111/211 Agenda Feb 17

Politechnika Krakowska im. Tadeusza Kościuszki. Karta przedmiotu. obowiązuje studentów rozpoczynających studia w roku akademickim 2013/2014

Zarządzanie Projektami Inwestycyjnymi

Call 2013 national eligibility criteria and funding rates

ROZPRAWY NR 128. Stanis³aw Mroziñski

Metodyki projektowania i modelowania systemów Cyganek & Kasperek & Rajda 2013 Katedra Elektroniki AGH

Cracow University of Economics Poland

SPRAWOZDANIE Z DZIAŁALNOŚCI RADY NADZORCZEJ PERMA-FIX MEDICAL S.A. ZA OKRES OD DNIA 1 STYCZNIA 2017 R. DO DNIA 31 GRUDNIA 2017 R.

SPRAWOZDANIE Z DZIAŁALNOŚCI RADY NADZORCZEJ PERMA-FIX MEDICAL S.A. ZA OKRES OD DNIA 1 STYCZNIA 2016 R. DO DNIA 31 GRUDNIA 2016 R.

Zarządzanie sieciami telekomunikacyjnymi

Financial results of Apator Capital Group in 1Q2014

POLITECHNIKA WARSZAWSKA. Wydział Zarządzania ROZPRAWA DOKTORSKA. mgr Marcin Chrząścik

Zarządzanie Projektami Inwestycyjnymi

Updated Action Plan received from the competent authority on 4 May 2017

SPRAWOZDANIE Z DZIAŁALNOŚCI RADY NADZORCZEJ PERMA-FIX MEDICAL S.A. ZA OKRES OD DNIA 01 STYCZNIA 2014 R. DO DNIA 31 GRUDNIA 2014 R.

European Crime Prevention Award (ECPA) Annex I - new version 2014

Knovel Math: Jakość produktu

Streszczenie rozprawy doktorskiej


Urbanek J., Jabłoński A., Barszcz T ssswedfsdfurbanek J., Jabłoński A., Barszcz T., Wykonanie pomiarów

What our clients think about us? A summary od survey results

PROGRAM STAŻU. Nazwa podmiotu oferującego staż / Company name IBM Global Services Delivery Centre Sp z o.o.

Exposure assessment of mercury emissions

POLAND TENDER. Zamieszczanie ogłoszenia: obowiązkowe. Ogłoszenie dotyczy: zamówienia publicznego. SEKCJA I: ZAMAWIAJĄCY

Fig 5 Spectrograms of the original signal (top) extracted shaft-related GAD components (middle) and

Evaluation of the main goal and specific objectives of the Human Capital Operational Programme

Raport bieżący: 44/2018 Data: g. 21:03 Skrócona nazwa emitenta: SERINUS ENERGY plc

Akademia Morska w Szczecinie. Wydział Mechaniczny

Machine Learning for Data Science (CS4786) Lecture11. Random Projections & Canonical Correlation Analysis

Helena Boguta, klasa 8W, rok szkolny 2018/2019

THEORETICAL STUDIES ON CHEMICAL SHIFTS OF 3,6 DIIODO 9 ETHYL 9H CARBAZOLE


Strategic planning. Jolanta Żyśko University of Physical Education in Warsaw

Towards Stability Analysis of Data Transport Mechanisms: a Fluid Model and an Application

How to run successfully Clinical Trial Project?

PLANY I PROGRAMY STUDIÓW

Tworzenie zintegrowanych strategii miejskich. Creation of integrated urban strategies? the example of the Krakow Functional Area

Investment expenditures of self-governement units in percentage of their total expenditure


Łukasz Reszka Wiceprezes Zarządu

Cracow University of Economics Poland. Overview. Sources of Real GDP per Capita Growth: Polish Regional-Macroeconomic Dimensions

Sargent Opens Sonairte Farmers' Market

Latent Dirichlet Allocation Models and their Evaluation IT for Practice 2016

SZACOWANIE KOSZTÓW ROBOCIZNY PRODUKCYJNEJ HARMONOGRAMU NA TLE JEGO OPÓŹNIEŃ CZASOWYCH

System optymalizacji produkcji energii

Financial support for start-uppres. Where to get money? - Equity. - Credit. - Local Labor Office - Six times the national average wage (22000 zł)

Poland Tenders. Przebudowa budynku OSP Nowym Lublińcu z przeznaczeniem na świetlicę wiejską z zapleczem. Nazwa. Miejscowość.

ANALIZA EKONOMICZNA BUDOWY I EKSPLOATACJI SYSTEMÓW TELEFONII INTERNETOWEJ W PRZEDSIĘBIORSTWIE ROLNICZYM

ZARZĄDZANIE JAKOŚCIĄ W ENERGETYCE

Employment. Number of employees employed on a contract of employment by gender in Company

Revenue Maximization. Sept. 25, 2018

Mgr Paweł Musiał. Promotor Prof. dr hab. n. med. Hanna Misiołek Promotor pomocniczy Dr n. med. Marek Tombarkiewicz

FORMULARZ OFERTY Nr... TENDER FORM No...

Standard pre-qualification form for contractors & suppliers. Formularz wstępny dla Wykonawców i Dostawców

Wykaz norm i innych dokumentów normalizacyjnych serii ISO i ich polskie odpowiedniki

Best practices in business process automation

PLANY I PROGRAMY STUDIÓW

PRZEWODNIK PO PRZEDMIOCIE. Negotiation techniques. Management. Stationary. II degree

Wydział Inżynierii Produkcji i Logistyki Faculty of Production Engineering and Logistics

Sustainable mobility: strategic challenge for Polish cities on the example of city of Gdynia

PROJECT. Syllabus for course Global Marketing. on the study program: Management

Uniwersytet Medyczny w Łodzi. Wydział Lekarski. Jarosław Woźniak. Rozprawa doktorska

Struktury proponowane dla unikalnych rozwiązań architektonicznych.

INSTYTUT GENETYKI I HODOWLI ZWIERZĄT POLSKIEJ AKADEMII NAUK W JASTRZĘBCU. mgr inż. Ewa Metera-Zarzycka

Health Resorts Pearls of Eastern Europe Innovative Cluster Health and Tourism

PRODUCTION HALL OFFER

ERASMUS + : Trail of extinct and active volcanoes, earthquakes through Europe. SURVEY TO STUDENTS.

INSPECTION METHODS FOR QUALITY CONTROL OF FIBRE METAL LAMINATES IN AEROSPACE COMPONENTS

Miejsce i rola organizacji międzynarodowych (w tym gospodarczych) w gospodarce światowej analiza wybranych przykładów GOSPODARKA ŚWIATOWA

Wykaz linii kolejowych, które są wyposażone w urządzenia systemu ETCS

SWPS Uniwersytet Humanistycznospołeczny. Wydział Zamiejscowy we Wrocławiu. Karolina Horodyska

XXIII Konferencja Naukowa POJAZDY SZYNOWE 2018

deep learning for NLP (5 lectures)

Medical electronics part 10 Physiological transducers

P R A C A D Y P L O M O W A

The analysis of the energy demand for heating and cooling of the house built on the basis of the traditional Canadian wood-frame construction

WEBINARIUM Tajna broń Project Managera - wprowadzenie do metody EVM

Stargard Szczecinski i okolice (Polish Edition)

PORTS AS LOGISTICS CENTERS FOR CONSTRUCTION AND OPERATION OF THE OFFSHORE WIND FARMS - CASE OF SASSNITZ

Wykaz linii kolejowych, które są wyposażone w urzadzenia systemu ETCS

Zakopane, plan miasta: Skala ok. 1: = City map (Polish Edition)

Karpacz, plan miasta 1:10 000: Panorama Karkonoszy, mapa szlakow turystycznych (Polish Edition)

DOI: / /32/37

The data reporting such indexes for a number of years (about twelve years of such data are were fitted to a logistic curve:

Innowacje społeczne innowacyjne instrumenty polityki społecznej w projektach finansowanych ze środków Europejskiego Funduszu Społecznego

Transkrypt:

TECHNICAL TRANSACTIONS 5/2017 CZASOPISMO TECHNICZNE 5/2017 CIVIL ENGINEERING DOI: 10.4467/2353737XCT.17.069.6426 Daniel Przywara (d.przywara@po.opole.pl) Adam Rak Department of Civil Engineering and Construction Processes, Faculty of Civil Engineering and Architecture, Opole University of Technology The time-cost analysis of schedule monitoring using the earned value method Analiza czasowo-kosztowa w monitoringu harmonogramu metodą wartości uzyskanej Abstract Maintaining the financial liquidity of construction companies during the implementation of large investment contracts is one of the main budgetary problems when planning their schedules. Despite the unquestioned, greater than ever, development of effective methods of planning, coordinating and controlling, the increase in the complexity of the organization's operating conditions makes it no easier to succeed in project management. This article attempts to analyse the impact of unplanned time and cost deviations on the liquidity of a construction project. Deviations from the planned costs and expenses incurred by the contractor were used as an example in this study. Keywords: Earned value method, time-cost deviation, schedule Streszczenie Utrzymanie płynności finansowej przedsiębiorstw budowlanych przy realizacji dużych kontraktów inwestycyjnych jest jednym z podstawowych problemów budżetowych przy planowaniu ich harmonogramów. Mimo niekwestionowanego, znaczniejszego niż kiedykolwiek rozwoju skutecznych metod planowania, koordynowania i kontrolowania, wzrost komplikacji warunków funkcjonowania organizacji powoduje, że osiągnięcie sukcesu w zarządzaniu projektami nie jest łatwiejsze. W artykule podjęto próbę analizy wpływu nieplanowanych odchyleń czasowych i kosztowych na płynność finansową przedsięwzięcia budowlanego. W badaniu odchyleń kosztów planowanych i kosztów poniesionych przez wykonawcę posłużono się przykładem zrealizowanej inwestycji. Słowa kluczowe: Metoda wartości uzyskanej, odchylenia czasowo-kosztowe, harmonogram 57

1. Introduction The implementation of construction projects is a specific and particularly difficult economic activity [3]. Exceeding of the assumed production costs, which is very often seen in the practice, causes that it is necessary to carry out research of the envisaged implementation conditions and chances of possible savings related to them. Searching for the possible investment scenario which is favourable for the contractor in terms of the works costs is a very complex issue. In practice, the problem is solved by using a simplified cost calculation which takes into account only costs as determined by cost analysis. They are intended to assess the organizational solutions, but not to assess the financial performance of the company [1]. Maintaining the liquidity of construction companies during the implementation of large investments is one of the main budgetary problems when planning the work schedules of construction projects [4]. Assessment of the tasks implementation by analysing deviations gives, in the case of cost accounting standards, a lot of useful information, such as variations in the quantity and value of the cross section of the calculation position (e.g. quantitative variation of direct materials, direct wage rates deviation) [3]. The selection of methods of production control depends upon many factors, especially: the degree of reproducibility of production, how detailed the available data is, how detailed the kept records are, use of planning and cadastral documentation, degree of use of computer techniques and the organisational culture prevailing in the company [6]. The earned value method (EVM) is considered to be an advanced control method for the projects which provides calculation results in the form of both quantitative and qualitative indicators [5]. EVM involves the control of the project by comparing executed scope of works along with their actual completion dates and the actual costs incurred with the adopted schedule and the project budget [6]. Compared with the traditional method of controlling progress of a construction project, EVM takes into account, apart from the planned and incurred costs, the so-called third dimension, i.e. the earned value which represents the planned value of the actually executed scope of works [2]. The basis of the earned value method is an indicator of earned value BCWP (budgeted cost of work performed). It is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period. To calculate it, it is necessary to have information on the planned cost of the work to be incurred as of the date of the inspection and the quantity of works actually performed [7]. The group of simple control indicators in this method includes: traditional variance TV: TV = BCWS ACWP (1) where BCWS budget cost of work scheduled, ACWP actual cost of work performed. 58

cost variance CV: where BCWP budget cost of work performed, ACWP as above. schedule variance SV: where BCWP as above, BCWS budget cost of work scheduled. CV = BCWP ACWP (2) SV = BCWP BCWS (3) In order to perform complex analysis of time and cost deviations, taking into account their impact on the liquidity of the project, the following additional parameters are introduced into the evaluation: the monitoring of changes in the assumed cash flow generated by deviation from the planned costs (T/C): T C TV BCWS ACWP / = = CV BCWP ACWP the monitoring of changes in the assumed cash flow generated by temporary deviation from the production plan (T/S): (4) TV BCWS ACWP T/ S= = SV BCWP BCWS where BCWP, BCWS, ACWP, TV, CV, SV as above. (5) 2. Application in engineering 2.1. Description of the test schedule To carry out monitoring of time and cost deviations, a financial and works schedule was used prepared for adding the first-floor to a medical building accommodating the regional blood centre. The construction contract included the following: the demolition of roofing (step 1); earthworks, together with the implementation of the staircase foundation system (steps 2 5); construction of the shell (steps 6 10); internal finishing works (actions 11 14); external finishing works (steps 15, 16); land development (steps 17, 18); repair works on the ground floor of the building (step 19). 59

The total duration of project including all the above steps was scheduled to be less than three months. Fig. 1 shows the works and financial schedule intended for implementation using the pipelined production method. Analyses were carried out using the Planista Max computer program, in the module Registration of works progress. Fig. 1. Beam Gantt schedule for the project. Source: Planista Max 2.2. Modelling of time and cost deviations of monitored works During the study of the impact of time and cost deviations on the financial liquidity of the project, three groups of computer models were developed, giving a total of twelve schedules in the four-scale of growth of the analysed parameter: Models A: of scenarios exceeding the planned budget costs (C), by 110%, 120%, 130%, 140%, while maintaining the planned duration of the project (S); Models B: of scenarios exceeding the planned duration of the project (S), by 105%, 110%, 115%, 120% while maintaining the planned budget costs (C); Models AB: of scenarios exceeding the planned budget costs (C), by 110%, 120%, 130%, 140% while exceeding the planned duration of the project (S) by 105% 110%, 115%, 120%. The results of the analysis, in the form of percentages, are summarised in Table 1. A graphical representation of the data is shown in Figures 2 10. Table 1. Models of schedules of analysed deviations Scenario of deviations Registration stage BCWP [PLN net] BCWS [PLN net] ACWP [PLN net] T/C [-] T/S [-] BCWS- ACWP [PLN net] A1: S = 100% C = 110% 30-06-2016 103 639.98 107 029.15 111 547.94 0.57 1.33-4 518.79 31-07-2016 513 825.27 515 752.93 566 761.25 0.96 26.46-51 008.32 31-08-2016 663 932.82 663 932.82 730 326.10 <0,00> <0,00> -66 393.28 60

A2: S = 100% C = 120% A3: S = 100% C = 130% A4: S = 100% C = 140% B1: S = 105% C = 100% B2: S = 110% C = 100% B3: S = 115% C = 100% B4: S = 120% C = 100% A1B1: S = 105% C = 110% A2B2: S = 110% C = 120% A3B3: S = 115% C = 130% A4B4: S = 120% C = 140% 30-06-2016 103 639.98 107 029.15 119 455.91 0.79 3.67-12 426.76 31-07-2016 513 825.27 515 752.93 619 697.23 0.98 53.92-103 944.30 31-08-2016 663 932.82 663 932.82 796 719.38 1.00 <0.00> -132 786.56 30-06-2016 103 639.98 107 029.15 127 363.87 0.86 6.00-20 334.72 31-07-2016 513 825.27 515 752.93 672 633.21 0.99 81.38-156 880.28 31-08-2016 663 932.82 663 932.82 863 112.67 1.00 <0.00> -199 179.85 30-06-2016 103 639.98 107 029.15 135 271.83 0.89 8.33-28 242.68 31-07-2016 513 825.27 515 752.93 725 569.19 0.99 108.85-209 816.26 31-08-2016 663 932.82 663 932.82 929 505.95 1.00 <0.00> -265 573.13 30-06-2016 99 686.00 107 029.15 103 639.98-0,86-0.46 3 389.17 31-07-2016 487 357.28 515 752.93 513 825.27-0.07-0.07 1 927.66 31-08-2016 630 736.18 663 932.82 663 932.82 0.00 0.00 0.00 30-06-2016 95 732.01 107 029.15 103 639.98-0.43-0.30 3 389.17 31-07-2016 460 889.29 515 752.93 513 825.27-0.04-0.04 1 927.66 31-08-2016 597 539.54 663 932.82 663 932.82 0.00 0.00 0.00 30-06-2016 91 778.03 107 029.15 103 639.98-0.29-0.22 3 389.17 31-07-2016 434 421.30 515 752.93 513 825.27-0.02-0.02 1 927.66 31-08-2016 564 342.90 663 932.82 663 932.82 0.00 0.00 0.00 30-06-2016 87 824.05 107 029.15 103 639.98-0.21-0.18 3 389.17 31-07-2016 406 677.73 515 752.93 513 825.27-0.02-0.02 1 927.66 31-08-2016 531 146.26 663 932.82 663 932.82 0.00 0.00 0.00 30-06-2016 99 686.00 107 029.15 111 547.94 0.38 0.62-4 518.79 31-07-2016 487 357.28 515 752.93 566 761.25 0.64 1.80-51 008.32 31-08-2016 630 736.18 663 932.82 730 326.10 0.67 2.00-66 393.28 30-06-2016 95 732.01 107 029.15 119 455.91 0.52 1.10-12 426.76 31-07-2016 460 889.24 515 752.93 619 697.23 0.65 1.89-103 944.30 31-08-2016 597 539.54 663 932.82 796 719.38 0.67 2.00-132 786.56 30-06-2016 92 295.44 107 029.15 127 363.87 0.58 1.38-20 334.72 31-07-2016 434 903.25 515 752.93 672 633.21 0.66 1.94-156 880.28 31-08-2016 564 342.90 663 932.82 863 112.67 0.67 2.00-199 179.85 30-06-2016 87 824.05 107 029.15 135 271.83 0.60 1.47-28 242.68 31-07-2016 407 017.66 515 752.93 725 569.19 0.66 1.93-209 816.26 31-08-2016 532 761.78 663 932.82 929 505.95 0.67 2.02-265 573.13 61

Fig. 2. Financial liquidity of the test project in models A1 A4 Fig. 3. Financial liquidity of the test project in models B1 B4 Fig. 4. Financial liquidity of the test project in models A1B1 A4B4 62

Fig. 5. Monitoring deviations from the assumed time in models A1 A4 Fig. 6. Monitoring deviations from the assumed time in models B1 B4 Fig. 7. Monitoring deviations from the assumed time in models A1B1 A4B4 63

Fig. 8. Monitoring deviations from costs in models A1 A4 Fig. 9. Monitoring deviations from costs in models B1 B4 Fig. 10. Monitoring deviations from costs in models A1B1 A4B4 64

3. Conclusions drawn from research and analysis A three-dimensional analysis of time and cost deviations using the value-added method parameters shows the influence of increase of the delay and budget exceeding value on the financial liquidity of the investment, not included in the classical form of this method. Analysis of pure liquidity calculated with the difference of costs incurred and planned in different periods (ACWP BCWS) is illustrated in A model group (Fig. 2), where the increasing amplitude in all three analyzed periods is observed. In the B model group (Fig. 3) with constant cost incurred, financial liquidity monitoring shows no change resulting from the gradual increase of delays. In AB models (Fig. 4) the amplitude values are equal to the scenarios of the progressive underestimation (A1 A4). The monitoring of time deviations from the planned schedule, in A model group reflects the influence of increasing cost deviation on the delay of the investment (Fig. 5). The time variances of the investigated schedule for the B model group (Fig. 6) grow in function of time, although in comparison to the declining financial liquidity, the highest negative value was recorded for the first period, decreasing to zero in the third period. An analysis of the complex scenario for models with both delay and underestimation (Fig. 7) gives similar form of monitoring of works execution: in this case, growing value of the time deviation give the result at the level of 2.00 in the third stage which means twice the difference in liquidity compared to BCWP in that period. Monitoring of deviations from costs in the A model group (Fig. 8) shows rising values, the highest in the third registration period, calculated by the ratio of disappearance of financial liquidity, in this case, to the difference in BCWP and ACWP values. Analysis of the results of the algorithm monitoring the cost deviation with gradual delay of the schedule (Fig. 9) shows negative deviation values, striving, with increasing time to zero. The attempt to simultaneously increase the underestimation with modeling of increasing delays (AB models, Fig. 10) gives the value of cost variances as in the A model group, reduced by the delayed execution of works in the schedule. References [1] Marcinkowski R., Metody rozdziału zasobów realizatora w działalności inżynieryjnobudowlanej, WAT, Warszawa 2002. [2] Nicholas M. J., Zarządzanie projektami, Wolters Kluwer Business, Warszawa 2012. [3] Nowak E., Zarządzanie kosztami i efektami, Wroclaw University of Economics, Wrocław 2011. [4] Przywara D., Rak A., Modelowanie płynności finansowej przedsięwzięcia budowlanego w kontekście założonych terminów odroczeń płatności, Zagadnienia Inżynierii Środowiska w Budownictwie, Opole 2016. [5] Przywara D., Rak A., Ocena odchyleń czasowych i kosztowych harmonogramu za pomocą metody wartości uzyskanej, Materiały Budowlane, Vol. 6/2016. 65

66 [6] Przywara D., Rak A., Szacowanie kosztów robocizny produkcyjnej harmonogramu na tle jego opóźnień czasowych, Civil and Environmental Engineering, Vol. 7/2016. [7] Trocki M., Nowoczesne zarządzanie projektami, P.W.E., Warszawa 2012.