Böschungsstabilisierung A1 HIGHWAY PYRZOWICE-PIEKARY ŚLĄSKIE, PL
A1 HIGHWAY PYRZOWICE-PIEKARY ŚLĄSKIE Böschungsstabilisierung Projekt Ort Land/Region A1 Highway Pyrzowice-Piekary Śląskie A1 Pyrzowice Piekary Śląskie Polen Installationsjahr 2011 Kunde Planer Ausführende Firma Weitere Unternehmen General Directorate of National Roads and Motorways Complex Project Sp. z o.o. / Transprojekt Kraków Sp. z o.o. BUDIMEX S.A. Stump-Hydrobudowa Sp. z o.o. / Italcementaciones S.L.U. / PPI Chrobok S.A. / ZRI Chrobok sp.j. Situation The Polish A1 highway connecting Poland from south to north leads through Silesia. Because of the morphology of the terrain, deep cuts were required. Due to geological conditions and also due to the fact that this area is strongly influenced by the hard coal mining activity, slope stabilization was a must. Massnahme For the following reasons designers together with the Polish National Roads selected TECCO SYSTEM³ as a stabilizing solution: - - - - complicated ground conditions about 12 geotechnical layers were described, only 4 of these were rocks and all others soil in different compositions there was an apprehension that after digging and taking off such mass of material, there will be a release of the energy and consequently, the slopes will be prone to collapse - which is quite common especially for such high slopes the system can be designed and dimensioned against superficial instabilities which offer the possibility to arrange the nails in a more economical way due to the capability of TECCO mesh in absorbing and transferring high loads when slopes stabilized with TECCO SYSTEM³ are combined with anti-erosion mats, they can regain a natural or vegetated appearance, which is aesthetically preferred. TECCO SYSTEM³ was designed to protect local instabilities of soil and rock masses. This worked perfectly, as first visible small movements occurred which were stopped by the TECCO mesh shortly after installation. Geschützte Objekte Strasse Systeme TECCO G65/3 Korrosionsschutz GEOBRUGG SUPERCOATING Geologie Marls, silts, sandstones and limestones. Fläche stabilisiert 180000 m² Maximale Hanghöhe 33 m Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 2/8
Hangneigung 30-34 Schutzmassnahmen Aktive Stabilisierung Hat Begrünung Ja Erosionsschutzmatte Ja Ausrichtung - Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 3/8
Deep cut along the A1 Highway between Pyrzowice and Piekary Śląskie - nailing and flexible facing using TECCO SYSTEM³ ensure safety and a natural look For the cuts along the highway the top down method with benching was applied. The benches were subsequently nailed and covered with TECCO SYSTEM³ To make the nailing as efficient as possible, some subcontractors used drill rigs installed on an excavator. This allowed drilling works flexibility Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 4/8
November 2010 - visible installation of self drilling TITAN nails To allow optimal TECCO SYSTEM³ pre-tensioning, nails were cut to the slope face and dells around were prepared Flexible facing using TECCO SYSTEM³ during installation, after the anti-erosion mats have been placed on the slope Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 5/8
TECCO SYSTEM³ partially installed - the pre-tensioning minimises the risk of further slope deformations Directly after nailing slope facing application, an extra layer of humus was applied to support further greening Thanks to the applied solutions, the greening came very fast and required only seeding Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 6/8
Closer look on the fully stabilized slopes - TECCO SYSTEM³ is nearly invisible and allows fast greening The highway after the opening Stabilized cut - thanks to the applied solutions, the slopes maintain their natural look Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 7/8
Für Fragen steht Ihnen unser Geobrugg Spezialist gerne zur Seite Alexander Barinov, Geographer PhD Tel. +7 495 760 72 38 Mobil +7 985 760 72 38 Alexander.Barinov@geobrugg.com Russland Generala Dorokhova st. 14 Moskau Russland info@geobrugg.ru www.geobrugg.ru A company of the BRUGG Group Certified to ISO 9001 Böschungsstabilisierung A1 Highway Pyrzowice-Piekary Śląskie, PL 8/8