1 PROGRESS IN PREPARATION OF POLISH RAILWAY INFRASTRUCTURE FOR EURO 2012 April 2010

2 COURSE OF INVESTMENT PROCESS Average time necessary to carry out the investment on railway section of km : - Studies from 1.5 to 2 years (economic and financial analyses, maps for design purposes, preparation of tender documentation for selecting contractor for preparing building and executive designs terms of reference) - Awarding contract to design office c-ca 6 months from call for tenders, provided no protests occur - Design documentation from 1.5 to 2 years (programming and spatial concept, building and excutive designs, environmental report with application for environmental decision, land purchase, application for location decision, preparation of tender documentation for awarding works contract terms of reference) - EU application (agreement with Center for EU Transport Projects) - Awarding the contract c-ca 6 months from call for tenders, provided no protests occur - Works execution c-ca 2 years for section of km of line, partly in urban area Total time necessary for project implementation c-ca 7.5 year In design and build type contract c-ca 5 years

3 PROCEDURES OF CONTRACT SIGNING The Management Board signs a contract: After acceptance of: over 20 mln PLN Supervisory Board of PKP Polskie Linie Kolejowe S.A. over 160 mln PLN General Assembly of PKP Polskie Linie Kolejowe S.A. over 200 mln PLN General Assembly of PKP Polskie Linie Kolejowe S.A. and the State represented by minister responsible for public finances (in wirting) After signing agreement for co-financing with Center for EU Transport Projects investments co-financed within Operational Programme Infrastructure and Environment (OP I&E ; POIiŚ) After signing agreement with Marshal s Dept. of Voivodeship investments co-financed within Regional Operational Programme

4 RANGE OF BUILDING WORKS Typical railway investments cover: - Replacement of tracs on stations and open routes, permanent way, improvement of track geometry and subgrade - Drainage system on stations, open routes and level crossings - Replacement of telecommunication and power supply devices - Elimination of modernisation of level crossings, construction of parallel roads or fly-overs, - Modernisation of existing engineering structures, buildings, and traffic controlling posts - Platforms and utility infrastructure - Elements of envionmental protection - Elimination of collisions with other networks.

5 INVESTMENTS OF PKP POLSKIE LINIE KOLEJOWE S.A. RELATED TO EURO 2012

6 RAILWAY LINES NOTIFIED TO MASTER PLAN OF PL 2012 N o Line N o Location 1. E 65 Warszawa Gdynia: LCC Nasielsk, LCC Ciechanów, LCC Działdowo, LCCTczew, Gdynia Station stage I 2. E 20 Warszawa Terespol: section Siedlce Terespol Stage I, LOT B, C, i D Realization to EURO 2012 [km] 232,00 95,00 3. E 20 Poznań railway Node and Poznań Główny Station 21,00 4. E 20 Rzepin State border 15,00 5. E 59 Wrocław Poznań: section Wrocław border of dolnośląskie voivodeship 6. L 1 Warszawa Łódź: Stage I i II, without section Łódź Widzew Łódź Fabryczna 7. E 30 Zgorzelec Medyka: a. section Zgorzelec Opole d. section Rzeszów Gr. Państwa 58,00 120,50 276,00 103,30 8. Warszawa Inner-city line and passenger halt WarszawaStadion 13,00 9. Warszawa Warszawa Gdańska Station and by-pass Józefinów Warszawa Gdańska 10. MPL Okęcie Warszawa International Air Harbour Okęcie: task 1 and 2 26,00 10, MPL Balice Kraków International Air Harbour Balice 12,00 LCC - Local Control Center 982,20

7 RAILWAY LINES COMPLETED TO 1 th of January 2010 N o Line N o Location Completion for EURO 2012 [km] 1 E 20 2 E 30 State border Rzepin * Poznań Railway Node Mińsk Mazowiecki Siedlce * Siedlce Łuków Łuków Międzyrzec Podlaski Międzyrzec Podlaski Biała Podlaska Biała Podlaska Terespol Zgorzelec Legnica Malczyce Szczedrzykowice Środa Śląska Wrocław Wrocław Opole Stacja Oława 15,00 21,00 52,00 23,35 24,20 20,80 25,86 97,00 6,00 43,00 104,00 3 E 65 Gdynia Station stage I 4 L 1 Łódź Widzew Skierniewice 62,80 5 WWK By-pass Józefinów Warszawa Gdańska 26,00 6 L 8 Warszawa Zach. Warszawa Okęcie 8,40 * Realized in 2007 r. tasks, account for to end 2008 r. 529,41

8 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol section: Rzepin state border Completed Section length 15 km Investment cost c-ca million Cofinancing ISPA/CF 75 %, state budget 25 % The project covered: construction of passenger stop in Słubice, reconstruction of Kunowice station, replacement of permanent way on 15 km of line, reconstruction of 15 km section of automatic line block and power supply devices, modernisation of traffic control devices, reconstruction of catenary system on the whole section, construction of two overpasses for animals.

9 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol section: Rzepin state border

10 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol Poznań Railway Node Completed Section length 21 km Estimated investment cost Cofinancing ISPA/CF 75 %, state budget 25 % The project covered: reconstruction of platforms reconstruction of pedestrian underpasses (adjustment for disabled people - elevators) modernisation of track layout modernisatio of drainage system replacement of catenary and power supply system installation of new traffic control system. renovation of 15 viaducts (including 2 structures as required by the National Conservation Office for Historic Monuments ) and 4 bridges, elimination of 3 level crossings and replacement by viaducts and underpasses replacement of 134 turnouts

11 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol Poznań Railway Node

12 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol section Siedlce Terespol Stage I: LOT A and C Planned completion 2009 Section length 95 km Estimated cost: million Cofinancing ISPA/CF 75 %, state budget 25 % LOT A Siedlce Łuków: completed LOT B Łuków Miedzyrzec Podl.: completed LOT C Międzyrzec Podl. Biała Podl.: completed LOT D Biała Podlaska Terespol: completed

13 MODERNISATION OF E 20 RAILWAY LINE Kunowice Terespol section Siedlce Terespol Stage I: LOT A and C

14 MODERNISATION OF E 30/CE 30 RAILWAY LINE Zgorzelec Medyka section State border - Opole Estimated completion 2010 Section length 276 km Estimated cost c-ca million PLN Cofinancing PHARE, EBI, ISPA/CF, TEN-T, state budget, PLK own resources MODERNIZACJA LINII KOLEJOWEJ E 30/CE 30 Zgorzelec Medyka odcinek gr. państwa - Opole Zgorzelec Legnica: completed Malczyce Szczedrzykowice: completed Środa Śląska Wrocław: completed Wrocław Opole: completed Stacja Oława: completed Most w Bolesławcu: completed

15 MODERNISATION OF E 30/CE 30 RAILWAY LINE Zgorzelec Medyka section State border - Opole Środa Śląska Malczyce, being implemented, planned completion the end of 2010 Advance of works: 47% Szczedrzykowice Legnica, being implemented, planned completion I q Advance of works: 85% Branch postszczedrzykowice, preparatory phase of investment, planned completion I q Advance: 76% MODERNIZACJA LINII KOLEJOWEJ E 30/CE 30 Advance of works: 68% Zgorzelec Medyka Miękinia Station, being implemented, planned completion II q. of 2010 Leśnica Station, preparatory phase of investment, planned completion III q Advance: 85% odcinek gr. państwa - Opole Brzeg Station, being implemented, planned completion the end of 2010 Advance of works: 48%

16 MODERNISATION OF E 30/CE 30 RAILWAY LINE Zgorzelec Medyka

17 MODERNISATION OF RAILWAY LINE N O 8 Warszawa Kielce section Warszawa Zach. Warszawa Okęcie Completed Section length 8.4 km Cost million PLN Cofinancing European Regional Development Fund (ERDF) for %, state budget 73.91% - 2 new passenger stops (Al. Jerozolimskie, Żwirki i Wigury) - Construction of reliable railway connection between Warsaw Center and Okęcie airport

18 MODERNISATION OF RAILWAY LINE N O 8 Warszawa Kielce section Warszawa Zach. Warszawa Okęcie Rebuilt the track for movement of suburban trains, on flyover in km before after

19 MODERNISATION OF RAILWAY LINE N O 8 Warszawa Kielce section Warszawa Zach. Warszawa Okęcie

20 MODERNISATION OF RAILWAY LINE N o 1 Warszawa Łódź Stage I: section Skierniewice Łódź Widzew Completed Section length 62.8 km Cost million PLN Cofinancing European Regional Development Fund (ERDF) for %, state budget 25 % The project covered: modernisation of stations: Skierniewice, Płyćwia, Rogów, passenger stops modernisation of tracks with adjustment of centerline distance to 4.0 m power sub-stations, sectioning cabins, level crossings, briges, viaducts overpasses, culverts, underpass in Rogów

21 MODERNISATION OF RAILWAY LINE N o 1 Warszawa Łódź Stage I: section Skierniewice Łódź Widzew

22 MODERNISATION OF WARSAW RAILWAY NODE By-pass W-wa Gdańska Józefinów At present Planned Speed 40 km/h 80 km/h Axle load 225 kn 225 kn Travel time cut of about 16 min Completed Section length 26 km Cost 127 million PLN Cofinancing state budget, PLK own resources Results: - by-pass for Linia Średnicowa (inner-city line) - present infrastructure cost reduction Additionally, construction of 3 new passenger stops with financial participation of Warsaw authorities (Powązkowska, Wola Park, Fort Wola) for EURO 2012

23 Length of lines remaining for completion to 2012 N o Line N o Location Completion for EURO 2012 [km] 1 E 65 Warszawa Gdynia 232,00 3 E 30 4 E 59 Legnica Środa Śląska Brzeg Station Rzeszów state border Wrocław border of dolnośląskie voivodeship 26,99 103,30 58,00 5 L 1 Warszawa Zach. Skierniewice 57,50 6 L 8 Warszawa Służewiec Airport Okęcie 2,00 7 WWK Warszawa Zach. Warszawa Wsch. 13,00 9 MPL Balice Kraków Airport Balice 12,00 504,79

24 MODERNISATION OF E 65 RAILWAY LINE Warszawa Gdynia Planned completion 2013 Section length km Estimated cost: Designing works c-ca th. Cofinancing ISPA/CF 75 %, state budget 25 % Stage I c-ca th. Cofinancing ISPA/CF 85 %, state budget 15 % Stage II c-ca th. Cofinancing ISPA/CF 84 %, state budget 16 % Stage III c-ca million PLN Cofinancing Operational Programme Infrastructure and Environment for Completion of about 232 km of lines planned to May 2012 Speed At present 120 km/h Planned Classic rolling stock160 km/h Tilting body train 200 km/h Axle load 196 kn 225 kn Travel time cut After completion of about 135 min

25 MODERNISATION OF E 65 RAILWAY LINE Warszawa Gdynia LCC Nasielsk: being implemented, Planned completion IV q Contract N o 8 (WPC Praga Legionowo, Nasielsk Station) Completed: 100% Contract N o 3a (Stations Legionowo, Nowy Dwór Maz., Modlin) Advance of works: 84% Contract N o 3b (routes) Advance of works: 62%

26 MODERNISATION OF E 65 RAILWAY LINE Warszawa Gdynia LCC Ciechanów: Planned completion IV q Contract N o 1a (Stations Gąsocin, Ciechanów; Routes Świercze Gąsocin, Gąsocin Ciechanów) Being implemented works were begun in October 2009 Advance of works: 20% Contract N o 1b (Stations Konopki, Mława; Routes Ciechanów Konopki, Konopki Mława) Preparatory phase of investment Advance: 85% Tender procedure lasts

27 MODERNISATION OF E 65 RAILWAY LINE Warszawa Gdynia LCC Działdowo: Planned completion II q Stations and routes Chosen Performer Planned signature contract II q Planned beginning works II q LCC Tczew: being implemented Planned completion 2010 Stations and routes Advance of works: 32% Gdynia Station stage I: completed Attention! Crossing have two planes did not become notified on EURO 2012, because deadlines of realization they go beyond apart from May 2012.

28 MODERNISATION OF E 59 RAILWAY LINE Wrocław Poznań section Wrocław border of Dolnośląskie Voivodeship Completion period 2014 r. Section length 58 km Estimated cost c-ca 1 522,366 million PLN Cofinancing Operational Programm Infrastructure and Environmentfor To May 2012 planned completion of routes At present Planned Speed 70 km/h 160 km/h Axle load 221 kn 221 kn ttravel time cut of about 20 min

29 MODERNISATION OF E 59 RAILWAY LINE Wrocław Poznań section Wrocław border of Dolnośląskie Voivodeship Skokowa Żmigród, being implemented, Planned completion II q Advance of works: 83% Wrocław Skokowa and Żmigród border of dolnośląskie voivodeship Preparatory phase of investment Planned completion of routes May 2012 Advance: 82%

30 MODERNISATION OF RAILWAY LINE N o 1 Warszawa Łódź Stage II: section Warszawa Zachodnia Skierniewice Planned completion II q Section length 57,5 km Estimated cost c-ca 1 790,0 million PLN Cofinancing Operational Programme Infrastructure and Environment for , State budget Preparatory phase of investment Advance: 81% Chosen Performer in system "project and build Planned signature contract II q At present Planned Speed 120 km/h 160 km/h Axle load 216 kn 225 kn Travel time after completion on section Warszawa Łódź 70 min.

31 MODERNISATION OF E 30/CE 30 RAILWAY LINE Zgorzelec Medyka section Rzeszów state border Completion time 2013 Section length km To May 2012 revitalisation to technical parameters of line V = 120 km/h Preparatory phase of investment Programme be worked out to the point - financial At present Planned Speed 80 km/h 120 km/h Axle load 196 kn 221 kn Elimination of speed limits

32 MODERNISATION OF WARSAW RAILWAY NODE Warszawa Stadion passenger halt and Warszawa Wschodnia Station Planned completion: Stage I Stage II po 2012 Section length 13 km At present Planned Speed 60 km/h 60 km/h Axle load 225 kn 225 kn Elimination of speed limits of 20/40 km/h Warszawa Wschodnia Station Preparatory phase of investment Advance: 62% Warszawa Stadion personal halt Preparatory phase of investment Advance: 70%

33 MODERNISATION OF WARSAW RAILWAY NODE Warszawa Stadion passenger halt and Warszawa Wschodnia Station The stage I, the range of works: Warszawa Wschodnia Station Provided for on EURO planned deadline of realization of works II q The estimated cost of realization of investment (the whole station) c-ca 720 million PLN The source of funding in track the, task notified to budget grant-in-aid defining on summer Planned choice performer I q Passenger halt Warszawa Stadion Provided for on EURO planned deadline of realization of works II q The estimated cost of realization of investment c-ca 90,0 million PLN The source of funding in track the, task notified to budget grant-in-aid defining on summer Planned choice performer III q. 2010

34 MODERNISATION OF WARSAW RAILWAY NODE Warszawa Gdańska Station Planned completion October 2010 Estimated cost ,94 PLN In this: PKP PLK S.A ,66 PLN Capital City Warszawa ,28 PLN Cofinancing State budget, PLK own resources Being implemented Advance of works: 29% Results: - Modernised station W-wa Gdańska connceted with metro station A17 through underpass At present Planned Speed 40 km/h 80 km/h Axle load 225 kn 225 kn Increase of station capacity from 90 to about 200 trains per day Warszawa Gdańska station after modernisation

35 RALIWAY CONNECTION TO AIRPORTS International Airport Warszawa Okęcie Completion II q Section length 2 km of tunnel Estimated cost mln zł Cofinancing Operational Programme Infrastrucutre and Environment for Being implemented Advance of works: 11% At present Planned Speed New section 60 km/h Axle load New section kn Travel time (min.) New section 20 min (from W-wa Centralna to the airport)

36 RALIWAY CONNECTION TO AIRPORTS International Airport Warszawa Okęcie Terminal II Okęcie Airport railway station, raw state Station visualisation, Terminal II Okęcie Airport Phase 3: works on tunnel link

37 RALIWAY CONNECTION TO AIRPORTS International Airport Kraków Balice Planned completion 2012 Section length 12 km Estimated cost mln zł Cofinancing Operational Programme Infrastructure and Environment for Stage I feasibility study and design documentation Being implemented Stage II works execution Planned contract awarding II q Planned works commencement III q Preparatory phase of investment Advance: 44% At present Planned Speed 60 km/h 80 km/h Axle load 221 kn 221 kn Travel time cut (in min.) to about 15 min

38 RALIWAY CONNECTION TO AIRPORTS International Airport Kraków Balice Passenger halt Kraków Balice One from operators' trainbusys line Kraków Główny Kraków Balice Kraków Balice passenger halt. Transfer to the bus transporting passengers to the airport terminal.

39 ALTERNATIVE (TO ROADS) RAILWAY CONNECTIONS Warszawa Wrocław Warszawa Centr. Wrocław Gł. through Centralna Magistrala Kolejowa (Central Trunk Line) with branch in Włoszczowa to Opole and Wrocław. Travel time reduction from Warszawa to Wrocław to 3 h 58 min. Improvement of technical condition speed increase to 120 km/h on section Włoszczowa Północ Opole Gł. Possible implementation 2011 Estimated cost: c-ca mln zł. No cofinancing Line N o Station 1 Warszawa Centralna 4 Grodzisk Mazowiecki 572 Włoszczowa Północ* 61 Żelisławice 144 Fosowskie 301 Bolko(PODG)* 132 Opole Główne 132 Wrocław Główny * Lines out of state importance

40 ALTERNATIVE (TO ROADS) RAILWAY CONNECTIONS Poznań Gdańsk Poznań Gł. Gdańsk Gł. through Inowrocław, Tczew Travel time reduction from Poznań to Gdańsk to 3 h 22 min. Improvement of technical condition speed increase to 120 km/h on section Poznań Gł. Tczew (section Tczew Gdańsk is modernised as a part of E 65) Possible implementation 2011 Estimatesd cost c-ca 821 mln zł. No sources of cofinancing Line N o Station 3 Poznań Główny 353 Poznań Wschód 131 Inowrocław 9 Tczew 9 Gdańsk Główny

41 Anticipated travel times between the EURO 2012 host cities (UEFA)

42 PROMOTION AND INFORMATION One of the first activities, layout for promoting investments for EURO 2012 with copy Kolej na Two versions existing: Basic for press publications and billboards For newspapaers, websites, computer presentations and gadgets

43 PROMOTION AND INFORMATION

44 PROMOTION AND INFORMATION radio and tv interviews press commercials TV spots Commercial campain on bilboards and busses in Euro 2012 host cities

45 PROMOTION AND INFORMATION

46 PROMOTION AND INFORMATION

47 gadgets PROMOTION AND INFORMATION

48 events PROMOTION AND INFORMATION

49 PROMOTION AND INFORMATION

50 PROMOTION AND INFORMATION

51 THANK YOU FOR YOUR ATTENTION!

STAN PRZYGOTOWAŃ POLSKIEJ INFRASTRUKTURY KOLEJOWEJ DO EURO 2012. Kwiecień 2010 r.

STAN PRZYGOTOWAŃ POLSKIEJ INFRASTRUKTURY KOLEJOWEJ DO EURO 2012. Kwiecień 2010 r. STAN PRZYGOTOWAŃ POLSKIEJ INFRASTRUKTURY KOLEJOWEJ DO EURO 2012 Kwiecień 2010 r. PRZEBIEG PROCESU INWESTYCYJNEGO NA KOLEI Średni czas potrzebny na przeprowadzenie procesu inwestycyjnego dla odcinka 60-80

Bardziej szczegółowo

Warszawa, luty 2012 r. www.plk-sa.pl

Warszawa, luty 2012 r. www.plk-sa.pl Description of the activity of PKP PLK S.A. and development perspective of Polish rail infrastructure Charakterystyka działalności PKP PLK S.A. oraz perspektywy rozwoju polskiej infrastruktury kolejowej

Bardziej szczegółowo

PRODUCTION HALL OFFER

PRODUCTION HALL OFFER PRODUCTION HALL OFFER 1. Name of production hall / Nazwa hali produkcyjnej Bałtowska 2. Location / Lokalizacja PRODUCTION HALL DATA Town / Street Miasto / Ulica Ostrowiec Świętokrzyski/Bałtowska Street

Bardziej szczegółowo

INVESTMENT PRIORITIES FOR TRANSPORT AND LOGISTC IN POLAND FOR YEARS 2007-2013

INVESTMENT PRIORITIES FOR TRANSPORT AND LOGISTC IN POLAND FOR YEARS 2007-2013 INVESTMENT PRIORITIES FOR TRANSPORT AND LOGISTC IN POLAND FOR YEARS 2007-2013 Republic of Poland Ministry of Infrastructure Tadeusz Jarmuziewicz,Secretary of State Frankfurt, May 20-21, 2008 EU FUNDS AVAILABLE

Bardziej szczegółowo

Space for your logo, a photograph etc. Action 3.3.1 (WBU) www.viaregiaplus.eu

Space for your logo, a photograph etc. Action 3.3.1 (WBU) www.viaregiaplus.eu Space for your logo, a photograph etc. Action 3.3.1 (WBU) THE ANALYSIS CONCERNING THE DESIGNATION OF THE ROUTE THAT INTEGRATES THE SOUTH OF THE LOWER SILESIA PROVINCE TOGETHER WITH NORTH - SOUTHLINKS Analiza

Bardziej szczegółowo

Financial support for start-uppres. Where to get money? - Equity. - Credit. - Local Labor Office - Six times the national average wage (22000 zł)

Financial support for start-uppres. Where to get money? - Equity. - Credit. - Local Labor Office - Six times the national average wage (22000 zł) Financial support for start-uppres Where to get money? - Equity - Credit - Local Labor Office - Six times the national average wage (22000 zł) - only for unymployed people - the company must operate minimum

Bardziej szczegółowo

Health Resorts Pearls of Eastern Europe Innovative Cluster Health and Tourism

Health Resorts Pearls of Eastern Europe Innovative Cluster Health and Tourism Health Resorts Pearls of Eastern Europe Innovative Cluster Health and Tourism Projekt finansowany Fundusze Europejskie z budżetu państwa dla rozwoju oraz ze Polski środków Wschodniej Unii Europejskiej

Bardziej szczegółowo

linii kolejowych w serwisie zamieszczonym w Internecie, bazującym na Interaktywnej Mapie Linii Kolejowych.

linii kolejowych w serwisie zamieszczonym w Internecie, bazującym na Interaktywnej Mapie Linii Kolejowych. 60 RAPORT ROCZNY Geoinformacja Geoinformation 2010 był kolejnym rokiem rozwoju geoinformacji w PKP Polskich Liniach Kolejowych S.A. Główne kierunki działań objęły prace związane z tworzeniem i rozbudową

Bardziej szczegółowo

LISTA REFERENCYJNA. 3 982 355,38 EUR (netto) 17 293 127,26 380 968 622,00 34 483 450,00. 27 724 414,16 EUR (brutto) 8 546 000,00 47 896 690,53

LISTA REFERENCYJNA. 3 982 355,38 EUR (netto) 17 293 127,26 380 968 622,00 34 483 450,00. 27 724 414,16 EUR (brutto) 8 546 000,00 47 896 690,53 LISTA REFERENCYJNA L.p. Zadanie Wartość robót Termin wykonania REALIZACJE ZAKOŃCZONE Z OSTATNICH 5 LAT 1. Wymiana rozjazdów wraz z robotami towarzyszącymi linie nr 1, 131 i 139 oraz wymiana szyn OC wraz

Bardziej szczegółowo

Awareness campaign Safe rail-road level crossing "Stop and Live!"

Awareness campaign Safe rail-road level crossing Stop and Live! Awareness campaign Safe rail-road level crossing "Stop and Live!" www.plk-sa.pl Geneva, 12-13 May 2014 The key objective of the campaign is: What are our objectives? - to promote the correct patterns of

Bardziej szczegółowo

DOŚWIADCZENIA W ZAKRESIE POSTĘPOWAŃ

DOŚWIADCZENIA W ZAKRESIE POSTĘPOWAŃ I INWESTYCJE PKP PLK S.A. ZWIĄZANE Z MODERNIZACJĄ LINII KOLEJOWYCH oraz DOŚWIADCZENIA W ZAKRESIE POSTĘPOWAŃ PRZETARGOWYCH DLA PROJEKTÓW KOLEJOWYCH WSPÓŁFINANSOWANYCH ZE ŚRODKÓW UNIJNYCH Warszawa, 11 marca

Bardziej szczegółowo

SUP 16/13 (AD 2 EPWA)

SUP 16/13 (AD 2 EPWA) OGRANICZENIE DOSTÊPNOŒCI LOTNISKA KRAKÓW/BALICE Z POWODU PRAC REMONTOWYCH NA RWY 07/25 LIMITED AVAILABILITY OF KRAKÓW/BALICE AERODROME DUE TO OVERHAUL WORKS ON RWY 07/25 STRONA 1-1 PAGE 1-1 POLSKA AGENCJA

Bardziej szczegółowo

Oferta przetargu. Poland Tender. Nazwa. Miejscowość. Warszawa Numer ogłoszenia. Data zamieszczenia 2011-09-28. Typ ogłoszenia

Oferta przetargu. Poland Tender. Nazwa. Miejscowość. Warszawa Numer ogłoszenia. Data zamieszczenia 2011-09-28. Typ ogłoszenia Poland Tender Oferta przetargu Nazwa Dostawa oprogramowania komputerowego umożliwiającego tworzenie opracowań statystycznych obrazujących gospodarowanie Zasobem Własności Rolnej Skarbu Państwa Miejscowość

Bardziej szczegółowo

BIAŁYSTOK LU BLIN RZESZÓW

BIAŁYSTOK LU BLIN RZESZÓW Sebastian Mech, PKP PLK S.A. PRAGUE 14 November 2007 High Speed planning in Poland. Preparation and implementation of high speed lines building. 1. Introduction A country the size of Poland needs efficient

Bardziej szczegółowo

Koleje Co zostało zrobione? Janusz Piechociński

Koleje Co zostało zrobione? Janusz Piechociński Koleje Co zostało zrobione? Janusz Piechociński Wykorzystanie przez PKP PLK S.A. funduszy Unii Europejskiej w projektach kolejowych perspektywy 2000-2006 W ramach funduszy przedakcesyjnych i akcesyjnych

Bardziej szczegółowo

Budynki i zabudowania na terenie (T/N) Buildings / other constructions on site (Y/N)

Budynki i zabudowania na terenie (T/N) Buildings / other constructions on site (Y/N) Poziom wód gruntowych [m] Underground water level [m] Czy były prowadzone badania geologiczne terenu (T/) Were geological research done (Y/) Ryzyko wystąpienia zalań lub obsunięć terenu (T/) Risk of flooding

Bardziej szczegółowo

Effective Governance of Education at the Local Level

Effective Governance of Education at the Local Level Effective Governance of Education at the Local Level Opening presentation at joint Polish Ministry OECD conference April 16, 2012, Warsaw Mirosław Sielatycki Ministry of National Education Doskonalenie

Bardziej szczegółowo

LISTA REFERENCYJNA. Termin wykonania REALIZACJE ZAKOŃCZONE Z OSTATNICH 5 LAT. 19 059 619,18 PLN (netto) 66 633 777,50 PLN (netto)

LISTA REFERENCYJNA. Termin wykonania REALIZACJE ZAKOŃCZONE Z OSTATNICH 5 LAT. 19 059 619,18 PLN (netto) 66 633 777,50 PLN (netto) LISTA REFERENCYJNA L.p. Zadanie Wartość robót 1. 2. 3. 4. 5. 6. 7. 8. 9. Przebudowa nawierzchni wraz z robotami towarzyszącymi na linii kolejowej 173 Rybnik Sumina, km 7,200 12,272 i tor nr 1, 12,305 13,353

Bardziej szczegółowo

Dofinansowanie UE. Data podpisania umowy (pierwotnej) Tytuł projektu. Wartość ogółem Wydatki kwalifikowane Dofinansowanie

Dofinansowanie UE. Data podpisania umowy (pierwotnej) Tytuł projektu. Wartość ogółem Wydatki kwalifikowane Dofinansowanie Lp Tytuł projektu Data podpisania umowy (pierwotnej) Wartość ogółem Wydatki kwalifikowane Dofinansowanie Dofinansowanie UE 1 2 3 4 5 6 7 8 Modernizacja linii kolejowej E 59 na odcinku Wrocław - Poznań

Bardziej szczegółowo

GLOBAL METHANE INITIATIVE PARTNERSHIP-WIDE MEETING 12-14.10.2011 Kraków, Poland

GLOBAL METHANE INITIATIVE PARTNERSHIP-WIDE MEETING 12-14.10.2011 Kraków, Poland GLOBAL METHANE INITIATIVE PARTNERSHIP-WIDE MEETING 12-14.10.2011 Kraków, Poland INSTITUTE OF TECHNOLOGY AND LIVE SCIENCES POZNAŃ BRANCH Department of Environmental Management in Livestock Buildings and

Bardziej szczegółowo

PRIORITY INVESTMENT PROJECTS ROAD TRANSPORT

PRIORITY INVESTMENT PROJECTS ROAD TRANSPORT 26 rivers ring roads main roads secondary roads streets railways Map prepared by: Miejski Zarząd Baz Danych PRIORITY INVESTMENT PROJECTS ROAD TRANSPORT 1 Extension and modernisation of road system at the

Bardziej szczegółowo

Umowa o współpracy ponadnarodowej

Umowa o współpracy ponadnarodowej Wzór minimalnego zakresu umowy o współpracy ponadnarodowej w ramach PO KL Umowa o współpracy ponadnarodowej Nazwa Programu Operacyjnego w Polsce: : Numer i nazwa Priorytetu: Numer i nazwa Działania: Numer

Bardziej szczegółowo

Oferta sprzedaży działki inwestycyjno- przemysłowej w Sieradzu (Greenfields for sale on urban economic zone in Sieradz)

Oferta sprzedaży działki inwestycyjno- przemysłowej w Sieradzu (Greenfields for sale on urban economic zone in Sieradz) Oferta sprzedaży działki inwestycyjno- przemysłowej w Sieradzu (Greenfields for sale on urban economic zone in Sieradz) Nazwa lokalizacji Site name Zakładników Miasto Town Sieradz Województwo Voivodship

Bardziej szczegółowo

BULLETIN 2 II TRAINING CAMP POLISH OPEN MTBO CHAMPIONSHIPS 19-22.06.2014 MICHAŁOWO 23-29.06.2014 TRAINING CAMP WORLD MTB ORIENTEERING CHAMPIONSHIPS

BULLETIN 2 II TRAINING CAMP POLISH OPEN MTBO CHAMPIONSHIPS 19-22.06.2014 MICHAŁOWO 23-29.06.2014 TRAINING CAMP WORLD MTB ORIENTEERING CHAMPIONSHIPS BULLETIN 2 II TRAINING CAMP POLISH OPEN MTBO CHAMPIONSHIPS 19-22.06.2014 MICHAŁOWO 23-29.06.2014 TRAINING CAMP WORLD MTB ORIENTEERING CHAMPIONSHIPS MASTERS WORLD MTB ORIENTEERING CHAMPIONSHIPS MTB ORIENTEERING

Bardziej szczegółowo

1987-2012 DYSKRET POLSKA 1987-2014

1987-2012 DYSKRET POLSKA 1987-2014 25 LAT 27 LAT 1987-2012 DYSKRET POLSKA 1987-2014 nasi klienci dobrze trafili... get your swing on with us... www.dyskret.com.pl 30-023 Kraków, ul. Mazowiecka 131 tel. +48 12 423 31 00, office@dyskret.com.pl

Bardziej szczegółowo

ITS project in Wroclaw Projekt ITS we Wrocławiu

ITS project in Wroclaw Projekt ITS we Wrocławiu ITS project in Wroclaw Projekt ITS we Wrocławiu Błażej Trzcinowicz ITS Project Manager Departament Prezydenta Zespół Zarządzania Projektami Department of the Mayor Project Management Unit Presentation

Bardziej szczegółowo

PORTS AS LOGISTICS CENTERS FOR CONSTRUCTION AND OPERATION OF THE OFFSHORE WIND FARMS - CASE OF SASSNITZ

PORTS AS LOGISTICS CENTERS FOR CONSTRUCTION AND OPERATION OF THE OFFSHORE WIND FARMS - CASE OF SASSNITZ Part-financed by EU South Baltic Programme w w w. p t m e w. p l PROSPECTS OF THE OFFSHORE WIND ENERGY DEVELOPMENT IN POLAND - OFFSHORE WIND INDUSTRY IN THE COASTAL CITIES AND PORT AREAS PORTS AS LOGISTICS

Bardziej szczegółowo

Rynkowe perspektywy dużych szybkości w Polsce zastosowanie projektu UIC dla krajów w Europy Centralnej i Wschodniej.

Rynkowe perspektywy dużych szybkości w Polsce zastosowanie projektu UIC dla krajów w Europy Centralnej i Wschodniej. Andrzej Żurkowski PKP SA Rynkowe perspektywy dużych szybkości w Polsce zastosowanie projektu UIC dla krajów w Europy Centralnej i Wschodniej. Market perspective for HST in Poland - implementation of UIC

Bardziej szczegółowo

Implementation of the JEREMIE initiative in Poland. Prague, 8 November 2011

Implementation of the JEREMIE initiative in Poland. Prague, 8 November 2011 Implementation of the JEREMIE initiative in Poland Prague, 8 November 2011 Poland - main beneficiary of EU structural funds - 20% of allocation within cohesion policy (EUR 67 bln) Over EUR 10 bln of NSRF

Bardziej szczegółowo

KATOWICE SPECIAL ECONOMIC ZONE GLIWICE SUBZONE and its influence on local economy KATOWICE SPECIAL ECONOMIC ZONE - GLIWICE SUBZONE

KATOWICE SPECIAL ECONOMIC ZONE GLIWICE SUBZONE and its influence on local economy KATOWICE SPECIAL ECONOMIC ZONE - GLIWICE SUBZONE KATOWICE SPECIAL ECONOMIC ZONE GLIWICE SUBZONE and its influence on local economy Definition: WHAT DOES THE SPECIAL ECONOMIC ZONE MEAN? THE SPECIAL ECONOMIC ZONE IS THE SEPERATED AREA WITH ATTRACTIVE TAX

Bardziej szczegółowo

Interfejs pomiędzy taborem a podsystemami Ruch, Sterowanie i Aplikacje telematyczne

Interfejs pomiędzy taborem a podsystemami Ruch, Sterowanie i Aplikacje telematyczne Interfejs pomiędzy taborem a podsystemami Ruch, Sterowanie i Aplikacje telematyczne Marek Pawlik, PKP PLK S.A. Interfejs RST do OPE, CCS i TAP Marek Pawlik, PKP PLK S.A. Tabela 9: Interfejs z podsystemem

Bardziej szczegółowo

2 nd ClimMani EU COST Action Meeting Poznań, Poland 28-30 September, 2015

2 nd ClimMani EU COST Action Meeting Poznań, Poland 28-30 September, 2015 nd ClimMani EU COST Action Meeting, oland 8-30 September, 015 Venue HOTEL MERCURE**** - OZNAŃ Address: ul. Roosvelta 0, 60-89, oland Tel. +48 61 855 80 00 e-mail: H3393@accor.com mercure-poznan-centrum.com

Bardziej szczegółowo

WAREHOUSE AND PRODUCTION HALL OFFER poz. schematu nr 1 position 1 on the sketch

WAREHOUSE AND PRODUCTION HALL OFFER poz. schematu nr 1 position 1 on the sketch WAREHOUSE AND PRODUCTION HALL OFFER poz. schematu nr 1 position 1 on the sketch PRODUCTION HALL DATA 1. Name of production hall / Nazwa hali produkcyjnej Hala magazynowo- produkyjna (oznaczona na schemacie

Bardziej szczegółowo

WAN S.A. P R E-L E T. Powierzchnia użytkowa (naziemna) 3 820 m Powierzchnia działki 1 865 m2. Usable surface 3 820 sq. m Area of the plot 1 865 sq.

WAN S.A. P R E-L E T. Powierzchnia użytkowa (naziemna) 3 820 m Powierzchnia działki 1 865 m2. Usable surface 3 820 sq. m Area of the plot 1 865 sq. WAN S.A. P R E-L E T Budynek Biurowy Gdańsk, ul. Śląska 12 Office Building - Gdansk, 12 Slaska Street OFERTA WYNAJMU LEASE OFFER Czynsz pow. biurowa 12 Euro/m2 Czynsz pow. usługowa 16 Euro/m2 Koszty eksploatacyjne

Bardziej szczegółowo

Urząd Marszałkowski Województwa Lubuskiego Departament Infrastruktury Społecznej Wydział Projektu Własnego w Obszarze Turystyki

Urząd Marszałkowski Województwa Lubuskiego Departament Infrastruktury Społecznej Wydział Projektu Własnego w Obszarze Turystyki Winnica Zabór - historia - 2010 Zabór Vineyard - history - 2010 (1) Spotkania spotkania spotkania Meetings Meetings Meetings Urząd Marszałkowski Województwa Lubuskiego Urząd Gminy Zabór Municipal Office

Bardziej szczegółowo

Economical utilization of coal bed methane emitted during exploitation of coal seams energetic and environmental aspects

Economical utilization of coal bed methane emitted during exploitation of coal seams energetic and environmental aspects Economical utilization of coal bed methane emitted during exploitation of coal seams energetic and environmental aspects President of The Board mgr inż. Roman Łój Katowicki Holding Węglowy S.A. Katowicki

Bardziej szczegółowo

www.investor.netia.pl Netia Network Infrastructure

www.investor.netia.pl Netia Network Infrastructure www.investor.netia.pl Netia Network Infrastructure Backbone Fiber Optics Infrastructure Backbone FO length 5000km 7 and 8 duct pipe standard in the backbone Minimum 6 duct pipe free resources in all most

Bardziej szczegółowo

POLISH ELEVATOR MARKET ONE YEAR AFTER JOINING EU

POLISH ELEVATOR MARKET ONE YEAR AFTER JOINING EU POLISH ELEVATOR MARKET ONE YEAR AFTER JOINING EU by Marek Oppeln-Bronikowski, 17 of March 2005, Brussels POLISH ECONOMICAL SITUATION POLISH ECONOMICAL SITUATION REAL ECONOMY: YEAR GDP CPI year-end Investment

Bardziej szczegółowo

Polish road development plan in clash with Natura 2000

Polish road development plan in clash with Natura 2000 Programming the EU funds for 200-201 Polish road development plan in clash with Natura 2000 Robert Cyglicki Krakow, Poland November 2-26, 200 1 21 1 Road infrastructure development plans until 201 Ko³baskowo

Bardziej szczegółowo

No matter how much you have, it matters how much you need

No matter how much you have, it matters how much you need CSR STRATEGY KANCELARIA FINANSOWA TRITUM GROUP SP. Z O.O. No matter how much you have, it matters how much you need Kancelaria Finansowa Tritum Group Sp. z o.o. was established in 2007 we build trust among

Bardziej szczegółowo

ŚCIANKI I PŁYTY PERONOWE

ŚCIANKI I PŁYTY PERONOWE ŚCIANKI I PŁYTY PERONOWE Prefabrykowane elementy peronu Płyta peronowa Ścianka peronowa Prefabrykowane elementy peronu p.o. Warszawa Aleje Jerozolimskie Ścianki i płyty peronowe produkowane w Przedsiębiorstwie

Bardziej szczegółowo

Project geoportal.gov.pl - implemented INSPIRE services

Project geoportal.gov.pl - implemented INSPIRE services Project geoportal.gov.pl - implemented INSPIRE services Dariusz Cieśla, Intergraph Polska (presenting author) Marcin Grudzień, CODGiK (presenting author) Marek Szulc, GUGiK Agenda Geoportal.gov.pl in short

Bardziej szczegółowo

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST Nazwa lokalizacji Site name

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST Nazwa lokalizacji Site name Położenie Location Powierzchnia nieruchomości Area of the property Informacje dotyczące nieruchomości Property information LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST Nazwa lokalizacji Site name Gdów

Bardziej szczegółowo

OKECIE BUSINESS POINT Oferta sprzedaży

OKECIE BUSINESS POINT Oferta sprzedaży OKECIE BUSINESS POINT Oferta sprzedaży Oferta budynku biurowego Warszawa, Sabały 60 Okęcie Business Point Office building offer Warsaw, Sabały 60 Street Okecie Business Point Witamy w 5th Avenue Holding

Bardziej szczegółowo

Planowanie zrównoważonego transportu miejskiego w Polsce. Sustainable Urban Mobility Planning Poland. Wprowadzenie. Introduction

Planowanie zrównoważonego transportu miejskiego w Polsce. Sustainable Urban Mobility Planning Poland. Wprowadzenie. Introduction Planowanie zrównoważonego transportu miejskiego w Polsce Sustainable Urban Mobility Planning Poland Wprowadzenie Introduction Wyzwania polityki UE w zakresie transportu miejskiego Zatłoczenie centrów miast

Bardziej szczegółowo

WAN S.A. P R E - L E T

WAN S.A. P R E - L E T WAN S.A. P R E - L E T Budynek Biurowy Gdańsk, ul. Śląska 12 Office Building - Gdańsk, 12 Śląska Street OFERTA WYNAJMU Czynsz pow. biurowa 12 euro/m 2 Czynsz pow. usługowa 16 euro/m 2 Koszty eksploatacyjne

Bardziej szczegółowo

Evaluation of the main goal and specific objectives of the Human Capital Operational Programme

Evaluation of the main goal and specific objectives of the Human Capital Operational Programme Pracownia Naukowo-Edukacyjna Evaluation of the main goal and specific objectives of the Human Capital Operational Programme and the contribution by ESF funds towards the results achieved within specific

Bardziej szczegółowo

Unit of Social Gerontology, Institute of Labour and Social Studies ageing and its consequences for society

Unit of Social Gerontology, Institute of Labour and Social Studies ageing and its consequences for society Prof. Piotr Bledowski, Ph.D. Institute of Social Economy, Warsaw School of Economics local policy, social security, labour market Unit of Social Gerontology, Institute of Labour and Social Studies ageing

Bardziej szczegółowo

ROBYG GROUP Presentation for investors Warsaw, 19th October, 2011

ROBYG GROUP Presentation for investors Warsaw, 19th October, 2011 ROBYG GROUP Presentation for investors Warsaw, 19th October, 2011 Niniejsza prezentacja nie podlega rozpowszechnianiu, bezpośrednio czy pośrednio, na terytorium albo do Stanów Zjednoczonych Ameryki, Australii,

Bardziej szczegółowo

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST Położenie Location Powierzchnia nieruchomości Area of property Cena Price Informacje dotyczące nieruchomości Property information Charakterystyka działki

Bardziej szczegółowo

LEARNING AGREEMENT FOR STUDIES

LEARNING AGREEMENT FOR STUDIES LEARNING AGREEMENT FOR STUDIES The Student First and last name(s) Nationality E-mail Academic year 2014/2015 Study period 1 st semester 2 nd semester Study cycle Bachelor Master Doctoral Subject area,

Bardziej szczegółowo

Regionalny SEAP w województwie pomorskim

Regionalny SEAP w województwie pomorskim ENNEREG International Conference Transfer of knowledge in the field of sustainable use of energy 22 May 2012, Wielkopolska Voivodship Office, Poznań, Poland Regionalny SEAP w województwie pomorskim Katarzyna

Bardziej szczegółowo

ROBYG GROUP 3Q 2011 Financial results Warsaw, 10th November, 2011

ROBYG GROUP 3Q 2011 Financial results Warsaw, 10th November, 2011 ROBYG GROUP 3Q 2011 Financial results Warsaw, 10th November, 2011 Niniejsza prezentacja nie podlega rozpowszechnianiu, bezpośrednio czy pośrednio, na terytorium albo do Stanów Zjednoczonych Ameryki, Australii,

Bardziej szczegółowo

Poland Tenders. Przebudowa budynku OSP Nowym Lublińcu z przeznaczeniem na świetlicę wiejską z zapleczem. Nazwa. Miejscowość.

Poland Tenders. Przebudowa budynku OSP Nowym Lublińcu z przeznaczeniem na świetlicę wiejską z zapleczem. Nazwa. Miejscowość. Poland Tenders Nazwa Przebudowa budynku OSP Nowym Lublińcu z przeznaczeniem na świetlicę wiejską z zapleczem Miejscowość Cieszanów Numer ogłoszenia 154129 Data zamieszczenia 2011-06-01 Typ ogłoszenia Ogłoszenie

Bardziej szczegółowo

Plan 1. WPROWADZENIE 2. WARUNKI ZALICZENIA 3. WYTYCZNE DO PROJEKTU 4. WYBÓR ODCINKA

Plan 1. WPROWADZENIE 2. WARUNKI ZALICZENIA 3. WYTYCZNE DO PROJEKTU 4. WYBÓR ODCINKA 1 Plan 1. WPROWADZENIE 2. WARUNKI ZALICZENIA 3. WYTYCZNE DO PROJEKTU 4. WYBÓR ODCINKA 2 WPROWADZENIE mgr inż. Aleksander Drzewiecki aleksander.drzewiecki@polsl.pl ul. Krasińskiego 13 p.003 tel. 32-603

Bardziej szczegółowo

www.interregiorail.eu info@interregiorail.eu

www.interregiorail.eu info@interregiorail.eu Transport publiczny w Legnicko Głogowskim Okręgu Miedziowym PUBLIC TRANSPORT IN LEGNICA- GŁOGÓW COPPER BELT (LGOM) Lubin, 06.10.2010 LGOM Charakterystyka regionu / Characteristic of the area Tworzony przez

Bardziej szczegółowo

POLAND TENDER. Zamieszczanie ogłoszenia: obowiązkowe. Ogłoszenie dotyczy: zamówienia publicznego. SEKCJA I: ZAMAWIAJĄCY

POLAND TENDER. Zamieszczanie ogłoszenia: obowiązkowe. Ogłoszenie dotyczy: zamówienia publicznego. SEKCJA I: ZAMAWIAJĄCY POLAND TENDER Złotów: Usługi kominiarskie wykonywane w budynkach administrowanych przez Miejski Zakład Gospodarki Lokalami w Złotowie Numer ogłoszenia: 422442-2009; data zamieszczenia: 09.12.2009 OGŁOSZENIE

Bardziej szczegółowo

Extraclass. Football Men. Season 2009/10 - Autumn round

Extraclass. Football Men. Season 2009/10 - Autumn round Extraclass Football Men Season 2009/10 - Autumn round Invitation Dear All, On the date of 29th July starts the new season of Polish Extraclass. There will be live coverage form all the matches on Canal+

Bardziej szczegółowo

POLSKA POŁOŻENIE KRAJOBRAZ TWOJEGO SUKCESU SITUATION ENVIRONMENT OF YOUR SUCCESS. Elbląg. Gdańsk 60 KM. Olsztyn 100 KM.

POLSKA POŁOŻENIE KRAJOBRAZ TWOJEGO SUKCESU SITUATION ENVIRONMENT OF YOUR SUCCESS. Elbląg. Gdańsk 60 KM. Olsztyn 100 KM. POŁOŻENIE KRAJOBRAZ TWOJEGO SUKCESU Gdańsk 60 KM Elbląg Kaliningrad 111 KM Olsztyn 100 KM ROSJA Elbląg położony jest: w północnej Polsce 60 km od Trójmiasta (Gdańsk, Sopot, Gdynia) w bezpośrednim sąsiedztwie

Bardziej szczegółowo

Łukasz Reszka Wiceprezes Zarządu

Łukasz Reszka Wiceprezes Zarządu Łukasz Reszka Wiceprezes Zarządu Time for changes! Vocational activisation young unemployed people aged 15 to 24 Projekt location Ząbkowice Śląskie project produced in cooperation with Poviat Labour Office

Bardziej szczegółowo

z dnia 15 października 2013 r. w sprawie zatwierdzenia Programu rzeczowo-finansowego wykorzystania środków Funduszu Kolejowego w latach 2014 2019

z dnia 15 października 2013 r. w sprawie zatwierdzenia Programu rzeczowo-finansowego wykorzystania środków Funduszu Kolejowego w latach 2014 2019 RM-111-184-13 U C H WA Ł A N R 1 8 4 / 2 0 1 3 R A D Y M I N I S T R Ó W z dnia 15 października 2013 r. w sprawie zatwierdzenia Programu rzeczowo-finansowego wykorzystania środków w latach 2014 2019 Na

Bardziej szczegółowo

Dom Development S.A., Pl. Piłsudskiego 3, 00-078 Warsaw

Dom Development S.A., Pl. Piłsudskiego 3, 00-078 Warsaw Jarosław Szanajca President of the Management Board Age: 45 Higher, Master of Law, Department of Law and Administration, Warsaw University 1996 present Dom Development S.A. in Warsaw, President of the

Bardziej szczegółowo

Recent Developments in Poland: Higher Education Reform Qualifications Frameworks Environmental Studies

Recent Developments in Poland: Higher Education Reform Qualifications Frameworks Environmental Studies 544524-TEMPUS-1-2013-1-PL-TEMPUS-SMHES Qualifications Frameworks for Environmental Studies at Ukrainian Universities Recent Developments in Poland: Higher Education Reform Qualifications Frameworks Environmental

Bardziej szczegółowo

Ewa Lewoczko Wspólny Sekretariat Techniczny INTERREG IV A w Löcknitz Joint Technical Secretariat INTERREG IV A in Löcknitz

Ewa Lewoczko Wspólny Sekretariat Techniczny INTERREG IV A w Löcknitz Joint Technical Secretariat INTERREG IV A in Löcknitz Program Operacyjny Celu 3 Europejska Współpraca Terytorialna - Współpraca Transgraniczna Krajów Meklemburgia-Pomorze Przednie/Brandenburgia i Rzeczpospolitej Polskiej (Województwo Zachodniopomorskie) 2007-2013

Bardziej szczegółowo

Final conference, 04-05.10.2011, Wrocław

Final conference, 04-05.10.2011, Wrocław Space for your logo, a photograph etc. DROGA ROWEROWA ŚW. JAKUBA NA DOLNYM ŚLĄSKU Way of St. James s cycling route in Lower Silesia Prezentacja działania projektu Via Regia Plus (akcja 5.3.3.) Presentation

Bardziej szczegółowo

Środki UE przeznaczone na transport w ramach POIiŚ

Środki UE przeznaczone na transport w ramach POIiŚ Współfinansowanie inwestycji infrastrukturalnych z funduszy europejskich w ramach Programu Operacyjnego Infrastruktura i Środowisko na lata 2007-2013 Jarosław Pasek, Dyrektor Departamentu Funduszy UE Warszawa,

Bardziej szczegółowo

Aktualny stan prac w zakresie budowy sieci Kolei Dużych Prędkości w Polsce,

Aktualny stan prac w zakresie budowy sieci Kolei Dużych Prędkości w Polsce, Aktualny stan prac w zakresie budowy sieci Kolei Dużych Prędkości w Polsce, Marek Pawlik Wiceprezes Zarządu PKP Polskie Linie Kolejowe S.A. Gdańsk, 13.10.2011 r. www.plk-sa.pl 1/23 KDP zakres i stan prac

Bardziej szczegółowo

Cel szkolenia. Konspekt

Cel szkolenia. Konspekt Cel szkolenia About this CourseThis 5-day course provides administrators with the knowledge and skills needed to deploy and ma Windows 10 desktops, devices, and applications in an enterprise environment.

Bardziej szczegółowo

Kolej siłą polskiej gospodarki Program spotkań wyjazdowych na linię E65. Opracowanie: Klub Budowlany Zespół Euro 2012 PKP PLK S.A.

Kolej siłą polskiej gospodarki Program spotkań wyjazdowych na linię E65. Opracowanie: Klub Budowlany Zespół Euro 2012 PKP PLK S.A. Program spotkań wyjazdowych na linię E65 Opracowanie: Klub Budowlany Zespół Euro 2012 PKP PLK S.A. 1 Wprowadzenie Wraz z rozwojem inwestycji w obszarze infrastruktury kolejowej będzie rosło zaufanie społeczne

Bardziej szczegółowo

Realizacja przez PKP Polskie Linie Kolejowe S.A. projektów infrastruktury kolejowej. Warszawa, 02 września 2016 r.

Realizacja przez PKP Polskie Linie Kolejowe S.A. projektów infrastruktury kolejowej. Warszawa, 02 września 2016 r. Realizacja przez PKP Polskie Linie Kolejowe S.A. projektów infrastruktury kolejowej Warszawa, 02 września 2016 r. Informacja na temat KPK perspektywa do roku 2023 Wartość KPK 66 mld PLN Główne cele Krajowego

Bardziej szczegółowo

EURO 2012 Championship in Krakow Traffic Management

EURO 2012 Championship in Krakow Traffic Management EURO 2012 Championship in Krakow Traffic Management Katarzyna Kyc Municipality of Krakow Urban Infrastructure Office - 741.510 inhabitants - 326,8 km² - 5.977 monuments - 41 museums - 16 theaters and music

Bardziej szczegółowo

Politechnika Krakowska im. Tadeusza Kościuszki. Karta przedmiotu. obowiązuje studentów rozpoczynających studia w roku akademickim 2014/2015

Politechnika Krakowska im. Tadeusza Kościuszki. Karta przedmiotu. obowiązuje studentów rozpoczynających studia w roku akademickim 2014/2015 Politechnika Krakowska im. Tadeusza Kościuszki Karta przedmiotu Wydział Inżynierii Środowiska obowiązuje studentów rozpoczynających studia w roku akademickim 014/015 Kierunek studiów: Inżynieria Środowiska

Bardziej szczegółowo

Your bridge to opportunities+

Your bridge to opportunities+ Goodman Wrocław IV 64,000 sqm warehouse space in strategic location Your bridge to opportunities+ Goodman Wrocław IV Wrocław, ul. Kwiatkowskiego Goodman Wrocław IV Wrocław, Kwiatkowskiego Street Zbliż

Bardziej szczegółowo

Mechanizmy wspierania rozwoju programu Galileo w innych krajach. Wybrane przykłady

Mechanizmy wspierania rozwoju programu Galileo w innych krajach. Wybrane przykłady Mechanizmy wspierania rozwoju programu Galileo w innych krajach Wybrane przykłady GATE - German GAlileo Test and Development Environment Centrum testowania Galileo Czas działania 2006-2010 Finansowanie:German

Bardziej szczegółowo

Cracow University of Economics Poland

Cracow University of Economics Poland Cracow University of Economics Poland Sources of Real GDP per Capita Growth: Polish Regional-Macroeconomic Dimensions 2000-2005 - Keynote Speech - Presented by: Dr. David Clowes The Growth Research Unit,

Bardziej szczegółowo

Osoby 50+ na rynku pracy 2013-1-PL1-GRU06-38713

Osoby 50+ na rynku pracy 2013-1-PL1-GRU06-38713 Osoby 50+ na rynku pracy 2013-1-PL1-GRU06-38713 Piąte spotkanie grupy partnerskiej w Katowicach (Polska) 19-20 maj 2015 Program Uczenie się przez całe życie Grundtvig Tytył projektu: Osoby 50+ na rynku

Bardziej szczegółowo

Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity

Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity Training and certification of Road Safety Experts for the application of Road Safety Audit and Road Safety Inspection

Bardziej szczegółowo

Wykaz maksymalnych prędkości - pociągi pasażerskie

Wykaz maksymalnych prędkości - pociągi pasażerskie Wykaz maksymalnych prędkości - pociągi pasażerskie W tablicy znajdującej się na kolejnych stronach tego załącznika zastosowano następujące oznaczenia: Nr - numer kolejowej według instrukcji Wykaz Id-12

Bardziej szczegółowo

Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity

Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity Zwiększanie Potencjału Na Rzecz Bezpieczeństwa Ruchu Drogowego Building Road Safety Capacity Management of Dangerous Road Sections in Estonia Andres Piibeleht Chief Specialist Traffic Management Department

Bardziej szczegółowo

THE PKP S.A. REAL ESTATE SECTION SUMMARY OF 2013

THE PKP S.A. REAL ESTATE SECTION SUMMARY OF 2013 THE PKP S.A. REAL ESTATE SECTION SUMMARY OF 2013 PROCESS IMPROVEMENT SPECIALIZED MARKET EXPERTS COMMERCIALIZATION, INVESTMENTS, EU FUNDS, SALES, MANAGEMENT PROCESS CENTRALIZATION MANAGEMENT BY OBJECTIVES

Bardziej szczegółowo

OFERTA INWESTYCYJNA NIERUCHOMOŚCI ZABUDOWANE INVESTMENT OFFER DEVELOPED PROPERTIES

OFERTA INWESTYCYJNA NIERUCHOMOŚCI ZABUDOWANE INVESTMENT OFFER DEVELOPED PROPERTIES OFERA IWESCJA IERUCHOMOŚCI ZABUDOWAE IVESME OFFER DEVELOPED PROPERIES PPU Port Rybacki Gryf Sp. z o.o. Regionalny Fundusz Gospodarczy S.A. Czerwiec 2011 June 2011 LISA DACH DOCZĄCCH EREU SIE CHECK LIS

Bardziej szczegółowo

THE INVESTMENT AREAS - BYTOM, LEŚNA STREET TERENY INWESTYCYJNE - BYTOM, ULICA LEŚNA

THE INVESTMENT AREAS - BYTOM, LEŚNA STREET TERENY INWESTYCYJNE - BYTOM, ULICA LEŚNA TERENY INWESTYCYJNE - BYTOM, ULICA LEŚNA Atrakcyjne tereny inwestycyjne znajdują się przy ul. Leśnej w Bytomiu, w bezpośrednim sąsiedztwie Alei Jana Nowaka-Jeziorańskiego. Przeznaczona do sprzedaży uzbrojona

Bardziej szczegółowo

Operating as if it was one common city Cross Border Cooperation on common infrastructure in the Twin City of Frankfurt (Oder) & Słubice

Operating as if it was one common city Cross Border Cooperation on common infrastructure in the Twin City of Frankfurt (Oder) & Słubice Operating as if it was one common city Cross Border Cooperation on common infrastructure in the Twin City of Frankfurt (Oder) & Słubice Sören Bollmann, Head of Frankfurt-Slubice Cooperation Center and

Bardziej szczegółowo

KAROLKOWA BUSINESS PARK

KAROLKOWA BUSINESS PARK KAROLKOWA BUSINESS PARK MAIN INFORMATION Class A office building NLA 17 647 sqm 11 floors Location: Warsaw, 30 Karolkowa Street (close Wola) 400 meters to the Metro station Rondo Daszyńskiego 260 parking

Bardziej szczegółowo

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST LISTA DAYCH DOTYCZĄCYCH TEREU SITE CHECK LIST Położenie Location Powierzchnia nieruchomości Area of property Cena Price Informacje dotyczące nieruchomości Property information Charakterystyka działki Land

Bardziej szczegółowo

Załącznik nr 1 do pisma APZX-630-27/ /12

Załącznik nr 1 do pisma APZX-630-27/ /12 Załącznik nr 1 do pisma APZX-630-27/ /12 SUPLEMENT NR../12 (ENR) Obowiązuje od 12-05-15 Obowiązuje do 12-07-15 1. ZAWARTOŚĆ SUPLEMENTU SUPPLEMENT No../12 (ENR) Effective from 12-05-15 Effective to 12-07-15

Bardziej szczegółowo

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST

LISTA DANYCH DOTYCZĄCYCH TERENU SITE CHECK LIST Położenie Location Powierzchnia nieruchomości Area of property Informacje dotyczące nieruchomości Property information Charakterystyka działki Land specification Nazwa lokalizacji Site name Miasto / Gmina

Bardziej szczegółowo

Lower Silesia Region CLIMATE-KIC PARTNER

Lower Silesia Region CLIMATE-KIC PARTNER Samorządowa jednostka organizacyjna Lower Silesia Region CLIMATE-KIC PARTNER Institute for Territorial Development / Climate-Kic 1 PRZEMYSŁAW MALCZEWSKI LOWER SILESIA COORDINATOR OF REGIONAL ACTIVITY AFFILIATED

Bardziej szczegółowo

WNIOSEK O PŁATNOŚĆ Nr/ APPLICATION FOR PAYMENT No.

WNIOSEK O PŁATNOŚĆ Nr/ APPLICATION FOR PAYMENT No. Annex no 8 to the Contract for the realization of the Project within the framework of the Lithuania, Poland and Kaliningrad Region of Russian Federation Neighbourhood Programme Standard form of payment

Bardziej szczegółowo

THE RAIL RATES valid from 1st October 2015

THE RAIL RATES valid from 1st October 2015 RAIL TARIFF This Rail Tariff is an integral part of intermodal transport arrangement service provided by PCC Intermodal S.A. and therefore it cannot be used as a standalone offer, only in combination with

Bardziej szczegółowo

SEGRO BUSINESS PARK WARSAW

SEGRO BUSINESS PARK WARSAW SEGRO BUSINESS PARK WARSAW OŻAROWSKA 40/42 DUCHNICE NOWOCZESNA POWIERZCHNIA BIZNESOWA MODERN BUSINESS SPACE 36 400 m 2 / 36,400 sq m SEGRO.pl SEGRO BUSINESS PARK WARSAW Nowoczesny park logistyczno-biznesowy

Bardziej szczegółowo

Sektor Kolejowy w Polsce The railway sector in Poland

Sektor Kolejowy w Polsce The railway sector in Poland Sektor Kolejowy w Polsce The railway sector in Poland SPIS TREŚCI TABLE OF CONTENTS INTRODUCTION 2 AN OVERALL CHARACTERISTICS OF THE RAILWAY INFRASTRUCTURE IN POLAND 4 WSTĘP 2 POLISH RAILWAY NETWORK COMPARED

Bardziej szczegółowo

Krytyczne czynniki sukcesu w zarządzaniu projektami

Krytyczne czynniki sukcesu w zarządzaniu projektami Seweryn SPAŁEK Krytyczne czynniki sukcesu w zarządzaniu projektami MONOGRAFIA Wydawnictwo Politechniki Śląskiej Gliwice 2004 SPIS TREŚCI WPROWADZENIE 5 1. ZARZĄDZANIE PROJEKTAMI W ORGANIZACJI 13 1.1. Zarządzanie

Bardziej szczegółowo